Name of project
|
State of preparation
|
Submission of Building Permit Application
|
Expected construction
|
|
D3 0310/I Úsilné – Hodějovice
|
Property settlement is under way – expropriation processes, archaeological research started in 04/2017; the first tender round for general contractor is being evaluated (2nd round expected to start in 08/2017)
|
building permit applications submitted for the entire main route, two permits issued out of nine
|
Q4/2017
|
|
D3 0310/II Hodějovice – Třebonín
|
Property settlement is under way (expropriation), archaeological research started in 04/2017; the first tender round for general contractor is being evaluated (2nd round expected to start in 08/2017)
|
building permit applications submitted for the entire main route in accordance with act No. 416/2009 Coll.
|
Q4/2017
|
|
D6 Lubenec bypass
|
All land purchased on the main route, a long-term dispute with Lubenské strojírny s.r.o. settled; the Office for Protection of Competition (ÚOHS) rejected the remedy – 1st round of the tender for the general contractor was evaluated (2nd round expected to start by the beginning of 06/2017)
|
the building permit application for the entire main route is in preparation
|
Q4/2017
|
|
D6 Nové Strašecí – Řevničov
|
Property settlement is under way – expropriation processes + settlement of land exchange – 100% of land on the main route has been handled and is ready for building permit issuance;the Office for Protection of Competition (ÚOHS) rejected the remedy – 1st round of the tender for the general contractor was evaluated (2nd round expected to start by the beginning of 06/2017)
|
the building permit application for the entire main route is in preparation
|
Q4/2017
|
|
D6 Řevničov bypass
|
Property settlement is under way – expropriation processes; remedy filed with the Office for Protection of Competition (ÚOHS) – this obstructs the evaluation of the 1st tender round and start of the 2nd round (expected beginning of 2nd round in 06/2017)
|
the building permit application for the entire main route is in preparation
|
Q4/2017
|
|
D11 1106 Hradec Králové – Smiřice
|
archaeological research has started, 1st round of the tender for the general contractor was evaluated (2nd round expected to start by the beginning of 06/2017)
|
before building permit issuance
|
Q3/2017
|
|
D11 1107 Smiřice – Jaroměř
|
Property settlement is under way – a church restitution dispute (the church refuses to give consent with the construction); archaeological research started; 1st round of the tender for the general contractor was evaluated (2nd round expected to start by the beginning of 06/2017)
|
building permit applications have been filed
|
Q4/2017
|
|
D35 Časy – Ostrov
|
Property settlement is under way – expropriation processes, archaeological research has been started; the first tender round for general contractor is being evaluated (2nd round expected to start by the beginning of 06/2017)
|
building permit application was filed for the entire main route
|
Q3/2017
|
|
D35 Opatovice nad Labem – Časy
|
Property settlement is under way – expropriation processes, archaeological research has been started; the first tender round for general contractor is being evaluated (2nd round expected to start by the beginning of 06/2017)
|
building permit application was filed for the entire main route
|
Q3/2017
|
|
D48 Frýdek Místek – bypass
|
building proceedings in progress, 100% of the land has been purchased, 1st round of the tender for the general contractor was evaluated (2nd round expected to start by the beginning of 06/2017)
|
building proceedings are under way
|
Q4/2017
|
|
D49 4901 Hulín – Fryšták
|
general contractor was selected
|
Building proceedings – legally effective exemption No.3 was granted for protected animals, a preliminary order was issued by the court for exemption No. 2 (hamster) (legally ineffective exemption)
|
Q4/2017
|
|
D55 5505 Otrokovice – south-east bypass
|
Property settlement in under way – there is an issue with the expropriation of husband and wife Gregůrkovy who submitted an expert opinion for a price over 2000 CZK/sqm. The expert opinion is incorrect; the usual price is one-tenth of that amount. ŘSD ČR disagrees with this expert opinion, the Expropriation Authority ordered an opinion review)
1st round of the tender for the general contractor was evaluated (2nd round expected to start in 08/2017)
|
The building permit application had been filed for the entire main route was withdrawn – an exemption from protected animals must be granted – application submitted with KÚ
|
Q4/2017
|
|
D1 0136 Říkovice – Přerov
|
Property settlement is under way – expropriation processes, a zoning permit amendment application was filed (04/2017; the exemption from protected animals was attacked, evaluation of the 1st tender round for general contractor is under way (2nd round expected to start in 11/2017)
|
the building permit application for the entire route in accordance with act No. 416/2009 Coll. is being prepared (it will be formally filed after the zoning permit amendment in about 07/2017);
|
Q1/2018
|
|
Modernisation of the railway line between Sudoměřice and Votice
|
The civil design is under development
|
08/2017
|
Q3/2017
|